A majority of uncertainty has its source in systems that lie outside the project,in its __________.

(Multiple Choice)
4.7/5
(31)

By and large,people respond to the goal-directedness of control systems in one of three general ways.Which of the following is not one of these ways?

(Multiple Choice)
4.9/5
(32)

An automatic control system containing a negative feedback loop is referred to as

(Multiple Choice)
4.9/5
(37)

Which of the following is the key feature of cybernetic control systems?

(Multiple Choice)
4.7/5
(26)

Change control systems,in some industries,are part of a firm's __________.

(Multiple Choice)
4.8/5
(28)

The cybernetic control system that acts to reduce deviations from standard is called a __________.

(Multiple Choice)
4.9/5
(35)

_________ is a management approach that may be used to make comparisons to "best in class" practices across organizations

(Multiple Choice)
4.8/5
(32)

__________ controls are usually viewed as helpful rather than as a source of unwelcome pressure if the controlees perceive themselves as able to perform inside the prescribed limits.

(Multiple Choice)
4.9/5
(35)

__________ are seen as much the same as a report card.

(Multiple Choice)
5.0/5
(41)

Thamhain (2013)found that ______was / were not only the most frequent risk class but also had the most impact on project performance.

(Multiple Choice)
4.9/5
(35)

For all but __________ changes,a risk identification and analysis should be performed.

(Multiple Choice)
4.8/5
(41)

In a cybernetic control system using a negative feedback loop,the speed or force with which the control operates is,in general,__________ to the size of the deviation from standard.

(Multiple Choice)
5.0/5
(41)

The critical ratio control chart uses a ratio made up of two parts -- the ratio of actual progress to scheduled progress,and the __________.

(Multiple Choice)
4.8/5
(33)

There are no purely mechanistic problems on projects.All problems have a _____ element,too.

(Multiple Choice)
4.8/5
(43)

When performing control,project managers need to be attentive to __________.

(Multiple Choice)
4.8/5
(38)

The most important rule for any subordinate is the Prime Law of Life on any project: __________.

(Multiple Choice)
4.9/5
(34)

With respect to financial controls,courts will require the practice of __________ regarding financial controls,practices,and record-keeping.

(Multiple Choice)
4.8/5
(36)

Identify some of the factors that can cause a project to require control of cost.

(Essay)
4.9/5
(40)

Describe the information requirements of a cybernetic controller.

(Essay)
4.9/5
(36)

A person with organizational clout who takes on personal responsibility for the successful completion of a project for the organization is referred to as a(n)__________.

(Multiple Choice)
4.8/5
(45)