Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis51 Questions
Exam 2: Introduction to Optimization and Linear Programming62 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet89 Questions
Exam 4: Sensitivity Analysis and the Simplex Method72 Questions
Exam 5: Network Modeling73 Questions
Exam 6: Integer Linear Programming73 Questions
Exam 7: Goal Programming and Multiple Objective Optimization62 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization69 Questions
Exam 9: Regression Analysis77 Questions
Exam 10: Discriminant Analysis60 Questions
Exam 11: Time Series Forecasting116 Questions
Exam 12: Introduction to Simulation Using Risk Solver Platform65 Questions
Exam 13: Queuing Theory80 Questions
Exam 14: Decision Analysis101 Questions
Exam 15: Project Management Online63 Questions
Select questions type
There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?
(Multiple Choice)
4.8/5
(31)
The following questions employ the AON network and partial spreadsheet below.
-Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?


(Multiple Choice)
4.9/5
(35)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?



(Short Answer)
4.9/5
(38)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.3. Identify each path through the network and its expected length.

(Essay)
4.8/5
(43)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.

(Essay)
4.9/5
(44)
What are the immediate predecessors of activity D in this network? 

(Multiple Choice)
4.8/5
(38)
What is the correct formula to compute the variance of an activity using PERT?
(Multiple Choice)
4.7/5
(34)
Non-critical activities are distinguished by the presence of
(Multiple Choice)
4.8/5
(39)
What is the earliest start time for activity D in the following diagram? 

(Multiple Choice)
4.9/5
(34)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?



(Essay)
4.8/5
(40)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?

(Essay)
4.9/5
(45)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. Identify each path through the network and its expected length.

(Short Answer)
4.8/5
(48)
If we are employing Activity-On-Arc (AOA) network design, the arcs in the network diagram represent
(Multiple Choice)
4.8/5
(41)