Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis51 Questions
Exam 2: Introduction to Optimization and Linear Programming62 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet89 Questions
Exam 4: Sensitivity Analysis and the Simplex Method72 Questions
Exam 5: Network Modeling73 Questions
Exam 6: Integer Linear Programming73 Questions
Exam 7: Goal Programming and Multiple Objective Optimization62 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization69 Questions
Exam 9: Regression Analysis77 Questions
Exam 10: Discriminant Analysis60 Questions
Exam 11: Time Series Forecasting116 Questions
Exam 12: Introduction to Simulation Using Risk Solver Platform65 Questions
Exam 13: Queuing Theory80 Questions
Exam 14: Decision Analysis101 Questions
Exam 15: Project Management Online63 Questions
Select questions type
The following questions employ the AON network and completed spreadsheet below.
-Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?


Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
C
What is the correct formula to compute the expected duration of an activity using PERT?
Free
(Multiple Choice)
4.8/5
(28)
Correct Answer:
D
What is the latest finish time for activity D in the following diagram? 

Free
(Multiple Choice)
4.8/5
(30)
Correct Answer:
B
What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts? 

(Multiple Choice)
4.8/5
(32)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?



(Essay)
4.9/5
(30)
What are the immediate successors of activity D in this network? 

(Multiple Choice)
4.8/5
(39)
In a PERT network the time required to complete a path is a(n)
(Multiple Choice)
4.9/5
(28)
Activity-on-Arc (AOA) networks do not allow multiple arcs with common start and finish nodes. If this must be represented, how is an AOA network modified?
(Multiple Choice)
4.8/5
(33)
The purpose of the backward pass in the Critical Path Method (CPM) technique is to
(Multiple Choice)
4.8/5
(27)
Consider the CPM network for the following set of activities:
-Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?

(Essay)
4.9/5
(42)
The following questions employ the AON network and partial spreadsheet below.
-Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?


(Multiple Choice)
4.9/5
(33)
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?


(Essay)
4.9/5
(30)
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?


(Essay)
4.8/5
(29)
The purpose of the forward pass in the Critical Path Method (CPM) technique is to
(Multiple Choice)
4.8/5
(34)
The longest path through a network is comprised of the ____ activities.
(Multiple Choice)
4.8/5
(36)
Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that
(Multiple Choice)
4.8/5
(28)
What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day? 

(Multiple Choice)
4.7/5
(34)
Showing 1 - 20 of 63
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)