Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis51 Questions
Exam 2: Introduction to Optimization and Linear Programming62 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet89 Questions
Exam 4: Sensitivity Analysis and the Simplex Method72 Questions
Exam 5: Network Modeling73 Questions
Exam 6: Integer Linear Programming73 Questions
Exam 7: Goal Programming and Multiple Objective Optimization62 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization69 Questions
Exam 9: Regression Analysis77 Questions
Exam 10: Discriminant Analysis60 Questions
Exam 11: Time Series Forecasting116 Questions
Exam 12: Introduction to Simulation Using Risk Solver Platform65 Questions
Exam 13: Queuing Theory80 Questions
Exam 14: Decision Analysis101 Questions
Exam 15: Project Management Online63 Questions
Select questions type
The following questions employ the AON network and partial spreadsheet below.
-Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?


(Multiple Choice)
4.9/5
(33)
Consider the CPM network for the following set of activities:
-Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?

(Essay)
4.8/5
(30)
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?


(Essay)
4.7/5
(34)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?



(Essay)
4.7/5
(29)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?



(Essay)
4.9/5
(38)
How many paths are there in the following project precedence network? 

(Multiple Choice)
4.8/5
(39)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.

(Essay)
4.8/5
(34)
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis? 

(Multiple Choice)
4.9/5
(33)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?

(Essay)
4.8/5
(29)
Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT)?
(Multiple Choice)
4.9/5
(34)
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?



(Essay)
4.9/5
(29)
Which of the following definitions correctly defines the acronym, PERT?
(Multiple Choice)
4.9/5
(34)
If we are employing Activity-On-Node (AON) network design, the arcs in the network diagram represent
(Multiple Choice)
4.8/5
(36)
If the following project must be completed by day 18 at minimum cost how do we change the LP model? 

(Multiple Choice)
4.9/5
(36)
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?


(Short Answer)
4.8/5
(33)
The following questions employ the AON network and completed spreadsheet below.
-Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?


(Multiple Choice)
4.9/5
(36)
Which of the following correctly describes the focus of the Critical Path Method (CPM)?
(Multiple Choice)
4.7/5
(32)
Consider the CPM network for the following set of activities:
-Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.



(Essay)
4.8/5
(44)
Showing 41 - 60 of 63
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)