Exam 7: Dependent Demand Inventory

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Answer the following. Answer the following.

(Essay)
4.8/5
(40)

Planned receipts are future orders that have not yet been released but are planned in order to avoid a shortage or backlog of inventory.

(True/False)
4.8/5
(38)

A bill of materials database is a basic output of an MRP system.

(True/False)
4.9/5
(42)

A product structure tree is often used to visually represent the.

(Multiple Choice)
4.9/5
(33)

The report for a work center that projects already scheduled and expected future capacity requirements against capacity availability is called.

(Multiple Choice)
4.8/5
(36)

Fixed order quantity lot size has a variable order size based on lead time.

(True/False)
4.9/5
(49)

Periodic order quantities are designed to order exactly the amount required for a specified period of time.

(True/False)
4.9/5
(28)

____ represent/represents orders that have been placed but not yet received or completed.

(Multiple Choice)
4.8/5
(32)

Give three examples of specific inventory transactions.

(Essay)
4.8/5
(36)

Scheduled receipts are the total number of units of a part derived from all parent production plans.

(True/False)
4.8/5
(37)

If 4000 six-pack colas are required,and 2000 six-packs are on hand,how many individual cans should be ordered if 3000 individual cans are also on hand?

(Essay)
4.8/5
(38)

An MRP system is static,that is,once a plan is created,it is seldom modified.

(True/False)
4.9/5
(41)

Every finished product has a bill of materials that specifies all components required to produce one unit of the finished product.

(True/False)
4.9/5
(34)

Recording inventory transactions accurately and promptly is a critical component of an effective MRP system.

(True/False)
4.8/5
(41)

A time bucket is the period in the future that is being planned.

(True/False)
4.8/5
(36)

Small changes to the bill of materials are normally not critical to the MRP system and have little impact on the final output.

(True/False)
4.8/5
(36)

Safety stock is excess inventory that a company holds to guard against uncertainty in demand,lead time,and supply.

(True/False)
4.8/5
(38)

Give three options a manager can take when a load report is generated which shows that more capacity is required than is available.

(Essay)
4.9/5
(34)

Provide three factors that may influence the lot size decision for a fixed order quantity.

(Essay)
4.8/5
(27)

Lead time is the estimate of the time between releasing an order and receiving the order,and is always known with certainty.

(True/False)
5.0/5
(39)