Service-oriented businesses typically experience a trade-off between the degree of sales opportunity and production efficiency.

Free
(True/False)
4.8/5
(31)
Correct Answer:
Verified

True

The time it takes to complete a particular step or action is

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
Verified

B

If an assembly process consists of 5 steps in series (activity A,activity B,activity C,activity D,and activity E),what is the utilization of the bottleneck activity if A takes 20 seconds,B takes 10 seconds,C takes 30 seconds,D takes 15 seconds,and E takes 5 seconds per unit?

Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
Verified

A

Gantt Charts,flowcharting,and bottlenecks are visual techniques to help analyze a process.

(True/False)
4.8/5
(30)

Comparing the number of products that must be produced to justify a given process is an example of

(Multiple Choice)
4.9/5
(36)

When selecting a process to improve,which of the following should be given priority?

(Multiple Choice)
4.8/5
(38)

Refer to the following break-even chart and describe what machines should be selected for various numbers of products. B.Machine 2 has the lowest cost if the number of products is between B and C.Machine 3 has the lowest cost if the number of products is between C and D.

(Essay)
4.8/5
(30)

A job shop is appropriate for products that are delivered in high volume.

(True/False)
4.8/5
(33)

What volume is required to break even if a product has fixed costs of $25,000,variable costs of $25 per unit,and the sales price is $40 per unit?

(Multiple Choice)
4.8/5
(35)

What are the three basic layout types?

(Short Answer)
4.9/5
(49)

Service-oriented businesses typically experience a trade-off between which of the following?

(Multiple Choice)
4.8/5
(26)

A fixed-position layout is appropriate for very large items,like a cruise ship.

(True/False)
4.8/5
(35)

Identify the four classifications of the service process matrix and provide an example of each.

(Essay)
4.9/5
(44)

The staff member at the airport money exchange booth has three main duties: exchanging money,making money orders,and wiring money.For the current layout,the staff member must travel 3 feet to exchange money.Money is exchanged about 20 times an hour and is a primary part of the job,so it is given a weight of 4.Making money orders require walking 10 feet and is done about 2 times per hour.Making money orders is given a weight of 2.Wiring money is done about 4 times an hour,has a weight of 3 and requires traveling 14 feet.What is the load distance score?

(Essay)
4.9/5
(30)

A car assembly operation is an example of a job shop.

(True/False)
4.9/5
(25)

The service process matrix differs along two dimensions: the degree of labor intensity and the degree of customer involvement.

(True/False)
4.7/5
(41)

Reengineering emphasizes the role of the process in producing goods.

(True/False)
4.9/5
(33)

If an assembly process consists of 5 steps in series (activity A,activity B,activity C,activity D,and activity E),what activity is the bottleneck if activity A takes 20 seconds,B takes 10 seconds,C takes 30 seconds,D takes 15 seconds,and E takes 5 seconds per unit?

(Multiple Choice)
4.8/5
(32)

Manufacturing processes can be described on a continuum where the volume for each type of product varies from low to high,whereas the reliability of customized goods varies conversely from high to low.

(True/False)
4.9/5
(36)

Describe the use of group technology.

(Essay)
4.9/5
(36)