Exam 8: Resourcing Projects
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles50 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS44 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects46 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick-Off45 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams46 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.What is the normal (un-crashed)duration of this project?

(Multiple Choice)
4.8/5
(42)
The process of estimating the types and quantities of material,human resources,equipment,or supplies required to perform each activity is called a "project staffing analysis."
(True/False)
4.8/5
(38)
Describe how crashing and fast tracking can be used to compress a project schedule.What limitations could there be with each of these methods?
(Essay)
4.9/5
(40)
When identifying people to work on the project,it is helpful to consider their professional disciplines,skill levels and their physical location.
(True/False)
4.9/5
(37)
Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.What is the incremental cost to achieve a one-day reduction in the duration of this project in the most cost efficient manner?

(Multiple Choice)
4.7/5
(45)
Showing 41 - 45 of 45