Exam 8: Resourcing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

  Figure 8-2 Software Programmer Loading Chart -Consider the software programmer loading chart presented in Figure 8-2.Which of the following statements most accurately describes the loading of the software programmer? Figure 8-2 Software Programmer Loading Chart -Consider the software programmer loading chart presented in Figure 8-2.Which of the following statements most accurately describes the loading of the software programmer?

(Multiple Choice)
4.7/5
(42)

Even when a project team does not identify individual activities,it will still need to determine how many resources are needed to complete the project

(True/False)
4.8/5
(26)

Critical Chain Project Management (CCPM)attempts to keep the most highly demanded resource busy on critical chain activities.

(True/False)
4.9/5
(30)

Crashing is a project schedule compression technique that relies extensively on overlapping activities and a high degree of concurrency.

(True/False)
4.9/5
(29)

  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.Which activity is an ideal candidate to delay in order to achieve a feasible schedule? Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.Which activity is an ideal candidate to delay in order to achieve a feasible schedule?

(Multiple Choice)
4.8/5
(39)

  Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.Who is accountable for the data requirements? Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.Who is accountable for the data requirements?

(Multiple Choice)
4.8/5
(31)

  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.How many programmers are required during the fifth week of this project? Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.How many programmers are required during the fifth week of this project?

(Multiple Choice)
4.8/5
(30)

Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team.

(True/False)
4.8/5
(41)

The critical chain method is a schedule method that modifies the critical path to account for limited resources.

(True/False)
4.7/5
(39)

  Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the cost to complete this project in the normal time? Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the cost to complete this project in the normal time?

(Multiple Choice)
4.8/5
(37)

What is a responsibility assignment matrix (RAM)? Describe how you might use a responsibility assignment matrix to manage the resources assigned to your project.

(Essay)
4.8/5
(40)

The staffing management plan addresses all of the following except:

(Multiple Choice)
4.8/5
(36)

Project managers must often face the challenge of compressing the project schedule.All of the following actions can be taken to reduce the duration of the critical path EXCEPT:

(Multiple Choice)
4.9/5
(31)

RACI (Responsible,Approve,Consult,Inform)charts go beyond a communication plan in that they identify every project activity and specify the exact involvement of each stakeholder.

(True/False)
4.7/5
(31)

When determining resource availability,project managers need only consider full-time,internal resources.

(True/False)
4.8/5
(44)

When project managers include diverse perspectives in making decisions,they can often avoid major risks that a single perspective would not uncover.

(True/False)
4.8/5
(40)

What should a project manager's considerations be when resourcing projects?

(Essay)
4.8/5
(43)

Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources.All of the following methods represent a potentially viable strategy to reduce work overloads EXCEPT:

(Multiple Choice)
4.9/5
(35)

A common tool project teams use is a responsibility assignment matrix (RAM).Typically,this chart will depict:

(Multiple Choice)
4.8/5
(35)

When recruiting resources to support a project,it is helpful to bring core team members and key subject matter experts on board as early as possible,to help plan the project and develop the project culture.

(True/False)
4.8/5
(30)
Showing 21 - 40 of 45