Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required. Annie is planning a large surprise party for her sister Gwendolyn. She has developed the following plan, including estimates of the time (in hours) and cost necessary to perform each of the tasks required.   What is Annie's total benefit from crashing this project? What is Annie's total benefit from crashing this project?

(Multiple Choice)
4.7/5
(32)

The customer has offered a $10,000 bonus if the project is completed within 14 days. What is the probability that the bonus will be earned?

(Multiple Choice)
4.8/5
(39)