Assuming that data exhibit a normal distribution,control limits set at ±\pm 3 standard deviations from the mean capture how much common variation?

(Multiple Choice)
4.9/5
(28)

The range of a data set is always non-negative.

(True/False)
4.9/5
(39)

Which of the following is the least important point to perform inspection?

(Multiple Choice)
4.8/5
(33)

If the average range is 4.0 inches and the sample size is 18,compute the upper and lower limits for an R chart.

(Essay)
4.8/5
(32)

The standard deviation measures the difference between the largest and smallest observations in a set of data.

(True/False)
4.8/5
(34)

The weight of a bag of sugar is an example of a variable.

(True/False)
4.8/5
(35)

The A2 factor includes how many standard deviations of ranges?

(Multiple Choice)
4.8/5
(31)

Ritz-Carlton employees are empowered to spend up to how much money on the spot to correct any customer complaint?

(Multiple Choice)
4.8/5
(35)

The computed AOQ provides a sense of the ______________ of the product

(Short Answer)
4.7/5
(33)

When should 100% inspection be used?

(Multiple Choice)
4.8/5
(32)

Descriptive statistics are used to describe quality characteristics and relationships.

(True/False)
4.9/5
(31)

Upper and lower control limits are usually set at ±\pm how many standard deviations from the mean?

(Multiple Choice)
4.9/5
(28)

Suppose a process has been monitored daily for the last ten days and the number of machine failures each day was noted.The results follow: Compute control limits for a c-chart that monitors the average number of machine failures per day.Is the process in a state of control?

(Essay)
4.9/5
(30)

Acceptance sampling occurs after the product has been produced.

(True/False)
4.8/5
(39)

An important task in quality control is to find out the range of natural random variation in a process.

(True/False)
4.8/5
(43)

What is the formula for an R chart's center line?

(Essay)
4.7/5
(39)

The person that comes from the top ranks of the organization and is responsible for providing direction and overseeing all aspects of a six-sigma implementation process is called a ________________________.

(Multiple Choice)
4.8/5
(37)

In six-sigma programs,individuals are given __________________ titles that reflect their skills in the six-sigma process.

(Multiple Choice)
4.8/5
(34)

What is a c-chart?

(Essay)
4.9/5
(37)

Consumers willingly accept defects if ________________________.