Exam 13: Installation and Operations
Exam 1: Introduction to Systems Analysis and Design103 Questions
Exam 2: Project Management157 Questions
Exam 3: Requirements Determination79 Questions
Exam 4: Business Process and Functional Modeling85 Questions
Exam 5: Structural Modeling94 Questions
Exam 6: Behavioral Modeling85 Questions
Exam 7: Moving on to Design99 Questions
Exam 8: Class and Method Design97 Questions
Exam 9: Data Management Layer Design93 Questions
Exam 10: Human Computer Interaction Layer Design80 Questions
Exam 12: Physical Architecture Layer Design74 Questions
Exam 12: Construction79 Questions
Exam 13: Installation and Operations94 Questions
Select questions type
There are three key roles in any major organizational change, the sponsor of the change, the change agent, and ___________.
(Multiple Choice)
4.8/5
(40)
The sponsor, the change agent, and the potential adopters are the actors found in the change management process.
(True/False)
4.8/5
(36)
Institutionalization refers to establishing formal post implementation deliverables for all projects.
(True/False)
4.9/5
(36)
If there are many users to train, many organizations turn to _____.
(Multiple Choice)
4.8/5
(32)
Direct conversion is the conversion style where both systems (as-is and to-be) are used simultaneously.
(True/False)
4.9/5
(33)
New programmers and systems analysts are typically assigned to work on complex new development projects.
(True/False)
4.9/5
(35)
Whole-system conversion is a better conversion strategy than modular conversion since the later one may introduce more bugs to the system during conversion.
(True/False)
4.8/5
(34)
One of the earliest models for managing organizational change was developed by Kurt Lewin. Lewin argued that change is a three-step process: unfreeze, change, refreeze.
(True/False)
4.9/5
(32)
Project assessment is not usually performed, yet it can be an important component of organizational learning.
(True/False)
4.7/5
(40)
The potential adopter is the person for whom the new system is designed and built.
(True/False)
4.9/5
(44)
The conversion location in which one or more locations are selected to test the conversion to the new system prior to full implementation is known as pilot conversion.
(True/False)
4.9/5
(41)
The most important factor associated with successful change is a(n) _____.
(Multiple Choice)
4.8/5
(35)
The installation of SAP to replace all of your legacy systems is an example of what type of conversion?
(Multiple Choice)
4.8/5
(40)
There are three important factors to consider in selecting a conversion strategy: risk, cost, and performance.
(True/False)