Multiple Choice
Which of the following is NOT a characteristic of the PERT method?
A) It assumes project activities are independent of each other and not affected by common factors.
B) Total project time TE) ) is assumed to have a normal distribution.
C) The distribution of possible times for an individual activity is described as a beta distribution.
D) Activity estimates are known and certain.
E) All of the above are characteristics of the PERT method.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Which of the following is an example
Q5: Which of the following types of precedence
Q6: The following network is the basis for
Q7: For the next two questions, refer to
Q8: A project team estimates that a work
Q10: For the next two questions, refer to
Q11: The following software development plan is the
Q12: The following information is the basis
Q13: Activity time estimates for the following project
Q14: Which of the following schedule display formats