Multiple Choice
The following network is the basis for the next four questions:
-Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project?
A) 3 days
B) 4 day
C) 5 days
D) 6 days
E) 7 days
Correct Answer:

Verified
Correct Answer:
Verified