The following software development plan is the basis for the next four questions
-The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame?
A) 54%
B) 67%
C) 75%
D) 93%
E) 100%
Correct Answer:

Verified
Correct Answer:
Verified