The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
-If the plumber and his crew begin working at 7:00 a.m., what time are they expected to finish?
A) 3:00 p.m.
B) 3:30 p.m.
C) 4:00 p.m.
D) 4:30 p.m.
E) 5:00 p.m.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: For the next two questions, refer to
Q8: A project team estimates that a work
Q9: Which of the following is NOT a
Q10: For the next two questions, refer to
Q11: The following software development plan is the
Q13: Activity time estimates for the following project
Q14: Which of the following schedule display formats
Q15: The following network is the basis for
Q16: The following network shows a portion of
Q17: The following network is the basis for