Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.
13.
Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11?
A) 100%
B) 75%
C) 50%
D) 25%
E) 10%