Multiple Choice
For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:
-Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C.
A) y = 4, z = 0
B) y = 0, z = 4
C) y = 0, z = 0
D) y = 4, z = 4
E) None of the above