Multiple Choice
The following software development plan is the basis for the next four questions
-The client has asked for an estimated completion date. What would you tell her?
A) 35 weeks
B) 41 weeks
C) 28 weeks
D) 21 weeks
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified