Multiple Choice
If there is more than one version of a document in circulation, what action should the Project Manager take?
A) Create a new version of the document and issue it to everybody.
B) Halt work until the correct version can be identified.
C) Recall all versions of the document.
D) Request a Product Status Account.
Correct Answer: