Multiple Choice
If a project is expected to be completed in 68 days with a project variance of 21 days,what is the probability that the project will be completed within 90 days?
A) between 5% and 10%
B) between 15% and 20%
C) between 25% and 30%
D) none of these
Correct Answer:

Verified
Correct Answer: