Multiple Choice
The cost of the project is given by ______.
A) multiplying the project's original budget by the reciprocal of the CPI
B) multiplying the project's original budget by the CPI
C) adding the project's original budget to the reciprocal of the CPI
D) adding the project's original budget to the CPI
Correct Answer:

Verified
Correct Answer:
Verified