Multiple Choice
Planned value is ______.
A) the total budget
B) a way to identify the expenditures at any one stage in the project
C) a cost estimate of the budgeted resources scheduled across the project's life cycle (cumulative baseline)
D) the real budgeted cost,or value,of the work actually performed to date
Correct Answer:

Verified
Correct Answer:
Verified