A PERT/CPM activity has an optimistic duration estimate of 3 days,a most likely duration estimate of 8 days,and a pessimistic duration estimate of 10 days.The expected duration of this activity te is:
A) 7.0
B) 7.5
C) 8.0
D) 8.5
E) 10.0