The amount of time an activity can be delayed and yet not delay the project is termed


A) Total slack.
B) Free slack.
C) Critical float.
D) Float pad.
E) Slip pad.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q71: The forward pass through a project network

Q87: Which of the following can be used

Q88: Which of the following is provided by

Q94: The forward pass in project network calculations

Q98: The activity time estimates used to build

Q100: When completing a backward pass, you carry

Q101: If a project has more than one

Q113: Which of the following is true about

Q116: When completing a forward pass, you carry

Q120: What is a lag and give an

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines