Multiple Choice
An estimate of the duration of a task that is based on a weighted average of a range of possible task durations is known as:
A) Most likely duration.
B) Expected duration.
C) Worst-case duration.
D) Probabilistic duration.
Correct Answer:

Verified
Correct Answer:
Verified