Multiple Choice
Another indicator of cost performance is cost variance (CV) .If the cumulative earned value is greater than the cumulative actual costs, then
A) the CV is positive.
B) the CV is equal to the TBC.
C) CV cannot be determined with CEV and CAC.
D) the CV is negative.
Correct Answer:

Verified
Correct Answer:
Verified