Exam 3: Managing the Information Systems Project
Exam 1: The Systems Development Environment100 Questions
Exam 2: The Origins of Software100 Questions
Exam 3: Managing the Information Systems Project97 Questions
Exam 4: Identifying and Selecting Systems Development Projects100 Questions
Exam 5: Initiating and Planning Systems Development Projects98 Questions
Exam 6: Determining System Requirements98 Questions
Exam 7: Structuring System Process Requirements100 Questions
Exam 8: Structuring System Data Requirements96 Questions
Exam 9: Designing Databases100 Questions
Exam 10: Designing Forms and Reports100 Questions
Exam 11: Designing Interfaces and Dialogues99 Questions
Exam 12: Designing Distributed and Internet Systems100 Questions
Exam 13: System Implementation95 Questions
Exam 14: Maintaining Information Systems99 Questions
Select questions type
The distinguishing feature of a network diagram is that the ordering of tasks is shown by connecting tasks-depicted as ________ or ovals-with their predecessor and successor tasks.
(Multiple Choice)
4.9/5
(26)
Resource estimates may need to be revised based upon the skills of the actual person (or people)assigned to a particular ________.
(Multiple Choice)
4.9/5
(38)
________ refers to the amount of time a task can be delayed without delaying the early start of any immediately following tasks.
(Multiple Choice)
4.9/5
(35)
Which of the following is NOT true of a project communication plan?
(Multiple Choice)
4.9/5
(36)
A Gantt chart is the graphical representation of a project that shows each task as a ________ bar whose length is proportional to its time for completion.
(Multiple Choice)
5.0/5
(36)
Systems development projects are undertaken for two primary reasons: to take advantage of business opportunities and to solve business problems.
(True/False)
4.8/5
(39)
The ________ is a systems analyst with a diverse set of skills-management,leadership,technical,conflict management,and customer relationship-who is responsible for initiating,planning,executing,and closing down a project.
(Multiple Choice)
4.8/5
(35)
________ is NOT a common skill pertaining to the leadership activity of a project manager.
(Multiple Choice)
4.9/5
(26)
An example of a project manager leadership activity is helping the team work towards a common goal.
(True/False)
4.8/5
(38)
A network diagram will never be used when the tasks ________.
(Multiple Choice)
4.8/5
(39)
To successfully orchestrate the construction of a complex information system,a project manager must have ________,leadership,and technical skills.
(Multiple Choice)
4.8/5
(34)
Getting projects completed through the effective utilization of resources is a ________ activity of a project manager.
(Multiple Choice)
4.8/5
(41)
________ is NOT a skill pertaining to the team management activity of a project manager.
(Multiple Choice)
4.9/5
(34)
In some organizations,the project manager is a very experienced systems analyst,whereas in others,both junior and senior analysts are expected to take on this role,managing parts of a project or actively supporting a more senior colleague who assumes the project manager role.
(True/False)
4.9/5
(29)
How many activities are involved in the project initiation phase?
(Multiple Choice)
4.9/5
(33)
________ is a controlled process of initiating,planning,executing,and closing down a project.
(Multiple Choice)
5.0/5
(31)
To construct the Gantt chart,a ________ is drawn for each activity that reflects its sequence and duration.