________ is a critical path scheduling technique used for controlling resources.

(Multiple Choice)
4.7/5
(26)

Tasks that are ________ in scope will provide a clear sense of the status of the project or of the interdependencies between tasks.

(Multiple Choice)
4.8/5
(21)

Define and describe the PERT technique.

(Essay)
4.7/5
(35)

A critical path refers to a sequence of task activities whose ________ and ________ directly affect the completion date of a project.

(Multiple Choice)
4.8/5
(34)

Identifying,assessing,and managing the risks and day-to-day changes that occur during a project is attributed to ________.

(Multiple Choice)
4.7/5
(38)

The critical path represents the ________ time in which a project can be completed.

(Multiple Choice)
4.9/5
(32)

Defining tasks in too much detail will make the management of the project ________.

(Multiple Choice)
4.9/5
(36)

What is the next step taken after project initiation?

(Multiple Choice)
4.9/5
(33)

Which of the following is NOT true about project closedown?

(Multiple Choice)
4.9/5
(34)

Which of the following is FALSE with respect to the Gantt chart and network diagram?

(Multiple Choice)
4.9/5
(35)

Executing the project is the third phase in the project management process.

(True/False)
4.7/5
(27)

Managing the project team for effective team performance represents a ________ activity of a project manager.

(Multiple Choice)
4.8/5
(45)

Which is the first activity in the project planning phase?

(Multiple Choice)
4.8/5
(35)

Designing and sequencing activities to attain project goals describes the technical problem solving activity.

(True/False)
4.7/5
(34)

Name four ways a project team can communicate.Indicate the type of formality,i.e.,high,medium to low,etc.

(Essay)
4.8/5
(27)

A study that determines if the proposed information system makes sense for the organization from an economic and operational standpoint is called non-feasibility study.

(True/False)
4.8/5
(28)

Most project management software tools support a broad range of task durations,including minutes,hours,days,weeks,and ________.

(Multiple Choice)
4.8/5
(36)