How does a vapor retarder under a concrete slab- on- ground affect the stresses caused by the shrinkage of the concrete slab?

Free
(Essay)
4.9/5
(32)
Correct Answer:
Verified

A vapor retarder, being a plastic sheet, provides a slip membrane, reducing the friction between the slab and the ground. Consequently, the slab is able to move more freely, reducing tensile stresses due to shrinkage.

In a typical site- cast reinforced- concrete structure, the cost of formwork and shores is

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

C

Height adjustability in shores made of dimension lumber

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
Verified

C

Scaffold- type shores are generally made from

(Multiple Choice)
4.7/5
(32)

A reinforced concrete column has vertical bars, referred to as longitudinal bars. Does a column need any other form of steel?

(Essay)
4.9/5
(32)

The tendons used for prestressing a PT concrete slab- on- ground generally consist of

(Multiple Choice)
4.8/5
(30)

Explain what a construction joint is.

(Essay)
5.0/5
(26)

Explain what a form- release agent is.

(Essay)
4.8/5
(34)

Aluminum is commonly used as form and shore material because

(Multiple Choice)
4.9/5
(39)

A PT concrete slab- on- ground may either be a ribbed slab or a constant- thickness slab.

(True/False)
4.9/5
(34)

The strength of concrete in a residential concrete slab- on- ground is generally

(Multiple Choice)
4.9/5
(33)

High- density overlay (HDO)on form plywood

(Multiple Choice)
4.8/5
(32)

List various types of reinforced- concrete slabs as described in this text, and explain the essential differences between them.

(Essay)
4.8/5
(38)

What are the advantages of prestressing?

(Essay)
4.9/5
(32)

A doubly reinforced beam is one in which

(Multiple Choice)
4.9/5
(35)

A construction joint in a concrete slab- on- ground is required if the concrete in the slab cannot be placed in one continuous operation.

(True/False)
4.8/5
(35)

Stirrups are generally made of

(Multiple Choice)
4.8/5
(31)

Name the items of the equipment used to pull the prestressing strands.

(Essay)
4.8/5
(33)

Explain what reshoring is.

(Essay)
4.8/5
(34)

What is the function of a drainage layer under a concrete slab- on- ground?

(Essay)
4.9/5
(34)
Showing 1 - 20 of 84