Exam 13: Project Evaluation and Control

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A project manager that uses milestones as a project control device is using a:

(Multiple Choice)
4.7/5
(43)

Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are:

(Multiple Choice)
4.9/5
(44)

The earned value divided by the actual, cumulative cost of the work to date is the:

(Multiple Choice)
4.8/5
(47)

Use this earned schedule table to determine the schedule variance (t) for this project at the end of Month 6. Use this earned schedule table to determine the schedule variance (t) for this project at the end of Month 6.

(Multiple Choice)
4.8/5
(36)

The closer to completion a project gets, the less precise and useful is the information that EVM provides.

(True/False)
4.8/5
(45)

Use the earned value table to determine the estimated time to completion given the indicated state of the project. Use the earned value table to determine the estimated time to completion given the indicated state of the project.

(Multiple Choice)
4.7/5
(36)

Take the factors considered by earned value analysis and subtract those considered by tracking Gantt charts. The factor(s) you have remaining are:

(Multiple Choice)
4.8/5
(33)

Use the information in the table regarding this seven-month project to calculate the SPI in terms of dollars and compare it with the SPI calculated in terms of time. Perform both calculations for months 1 through 6. Then use the SPI(t) to provide the Estimate at Completion for Time (EACt). Use the information in the table regarding this seven-month project to calculate the SPI in terms of dollars and compare it with the SPI calculated in terms of time. Perform both calculations for months 1 through 6. Then use the SPI(t) to provide the Estimate at Completion for Time (EAC<sub>t</sub>).

(Essay)
4.8/5
(41)

Planned value is:

(Multiple Choice)
4.9/5
(41)

In earned value management, schedule variance is defined as:

(Multiple Choice)
4.7/5
(34)

What are the problems with milestones as a project control mechanism?

(Essay)
4.9/5
(42)

Positive variance on an S-curve represents significant project progress.

(True/False)
4.8/5
(46)

  -Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. -Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.

(Multiple Choice)
4.9/5
(38)

Earned value management jointly considers the impact of:

(Multiple Choice)
4.8/5
(39)

The project baseline is established by combining data from the:

(Multiple Choice)
4.8/5
(33)

Briefly describe any seven critical success factors for project success contained in the Project Implementation Profile.

(Essay)
4.8/5
(42)

  -At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. -At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.

(Multiple Choice)
4.9/5
(33)

An excellent way to coordinate schedules with vendors and suppliers is through the use of:

(Multiple Choice)
4.9/5
(37)

A tracking Gantt chart:

(Multiple Choice)
4.8/5
(26)

Can earned value be used to manage a portfolio of projects? If so, how would this analysis proceed?

(Essay)
4.7/5
(41)
Showing 81 - 100 of 104
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)