Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
What is project crashing and what are three reasons why it might be important to do so?
Free
(Essay)
4.7/5
(40)
Correct Answer:
The process of accelerating a project is referred to as crashing. Crashing a project directly relates to resource commitment. The more resources we are willing to expend, the faster we can push the project to its finish. There can be good reasons to crash a project, among them are:
The initial schedule may be too optimistic.
Market needs change and the project is in demand earlier than anticipated.
The project has slipped considerably behind schedule.
The contractual situation provides even more incentive to avoid schedule slippage.
Which of these approaches will NOT accelerate the completion of a project?
Free
(Multiple Choice)
4.8/5
(45)
Correct Answer:
B
-Use the Gantt chart and activity list to determine which resource is used the least. 


Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
D
-Use the Gantt chart and activity list to determine which resource is used the most. 


(Multiple Choice)
4.7/5
(40)
-Use the Gantt chart and activity list to determine which resource is used the most. 


(Multiple Choice)
4.8/5
(36)
How might a project manager alter a straightforward PERT network to accommodate an inordinately large and complex project?
(Essay)
4.9/5
(39)
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
(True/False)
4.9/5
(36)
The most common type of logical sequencing between tasks is referred to as the:
(Multiple Choice)
4.9/5
(33)
In order to accelerate completion of a project, the manager must crash critical path activities.
(True/False)
4.7/5
(38)
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project as quickly as possible? 

(Multiple Choice)
4.8/5
(33)
The most common method for shortening activity durations involves the decision to:
(Multiple Choice)
4.9/5
(38)
-Use the Gantt chart and the activity list to determine which resource is used the least. 


(Multiple Choice)
4.8/5
(20)
-Use the Gantt chart and the activity list to determine when resource 5 is free. 


(Multiple Choice)
4.7/5
(38)
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000, what is the slope for the activity?
(Multiple Choice)
4.8/5
(34)
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown. Which statement is BEST? 

(Multiple Choice)
4.8/5
(26)
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
(True/False)
4.8/5
(34)
-Use the Gantt chart and the activity list to determine when resource 2 is free. 


(Multiple Choice)
4.9/5
(34)
Showing 1 - 20 of 96
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)