Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
"If anything can go wrong it often will" is an articulation of:
(Multiple Choice)
4.8/5
(35)
Which of these indirect costs is typically classified as an overhead cost?
(Multiple Choice)
4.9/5
(32)
An early warning signal for the potential of an overdrawn budget is created when:
(Multiple Choice)
4.8/5
(31)
A learning rate of 90% means that for every doubling of output, the time required by the activity falls by 10%.
(True/False)
4.9/5
(33)
Define learning curve theory and describe how learning curves are used in project management.
(Essay)
4.8/5
(39)
When asked to provide an estimate of an irrigation system, Pete looked from one end of the field to the other, licked a finger and held it in the air, squinted into the sun and said $25,000, give or take 30%. The technique employed for cost estimation is:
(Multiple Choice)
4.9/5
(37)
Activity-based costing is based on the notion that projects consume activities and activities consume resources.
(True/False)
4.9/5
(31)
A time-phased budget allocates costs across both project activities and the anticipated time in which the budget is to be expended.
(True/False)
4.8/5
(43)
A budget containing disaggregated figures across the schedule when work is planned is a:
(Multiple Choice)
4.9/5
(41)
Unplanned costs incurred when steps are taken to speed up a project's completion are called:
(Multiple Choice)
4.9/5
(40)
What is the total amount budgeted for March in this time-phased budget? 

(Multiple Choice)
4.7/5
(37)
What are four major categories of costs? Provide descriptions for each category.
(Essay)
4.8/5
(39)
You are probably looking at a bill for a variable cost when you are paying for:
(Multiple Choice)
4.9/5
(28)
A common reason for cost overruns in a project is a low initial estimate of project cost.
(True/False)
4.9/5
(38)
Showing 61 - 80 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)