Having too many people assigned to a task can sometimes cause more problems than it solves, both administratively and financially.

Free
(True/False)
4.9/5
(35)
Correct Answer:
Verified

True

You can choose between all four task dependencies in the ________ dialog box.

Free
(Short Answer)
4.7/5
(37)
Correct Answer:
Verified

Task Dependencies

Project can generate WBS numbering codes to identify the levels of decomposition for each task level.

Free
(True/False)
4.9/5
(43)
Correct Answer:
Verified

True

"Always track by entering the percent of work complete" is the ________ accurate method of tracking.

(Short Answer)
4.8/5
(39)

To specify a day as non- working time, click on________ .

(Short Answer)
4.8/5
(42)

The________ column allows to specify the units of a material resource.

(Short Answer)
4.9/5
(38)

In Microsoft Project, you can specify working times for individual resources that are different from the project's normal working time.

(True/False)
4.9/5
(33)

In Microsoft Project, once a critical path task has been completed, it is no longer considered a critical task.

(True/False)
5.0/5
(33)

The first time you assign resources to a task, Project calculates the duration of the task by multiplying the work required to complete the task by the percentage of work units.

(True/False)
4.8/5
(38)

For task durations, the default in Microsoft Project is:

(Multiple Choice)
4.9/5
(36)

Always track by entering the actual work done and work remaining is the fastest but least accurate method of tracking progress in Microsoft Project.

(True/False)
4.9/5
(37)

Microsoft Project determines the start and finish dates and times for each task based on the project's estimated start date, working on nonworking times, and task________ .

(Short Answer)
4.9/5
(28)

You can group tasks into a summary task using the ________ link.

(Short Answer)
4.8/5
(31)

When scheduling tasks in Microsoft Project, you should always set the start and finish dates.

(True/False)
4.8/5
(29)

In the earned value report, Microsoft Project uses________ to indicate the actual cost (AC).

(Multiple Choice)
5.0/5
(41)

Once you have specified all resources and determined the working times, you can________ .

(Short Answer)
5.0/5
(33)

Material resources include software and equipment, but not transportation to and from the job site.

(True/False)
4.9/5
(43)

What is not among the options in the "Change Working Time" dialog?

(Multiple Choice)
4.9/5
(36)

Before entering material resources, you will have to enter the column "Type" into the resource table.

(True/False)
4.8/5
(27)

To enter tasks, you can either input them directly or________ .

(Short Answer)
4.8/5
(40)