Exam 12: Managing Project Control and Closure

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

_________are approved and authorized actions that are recommended to correct defects in the project deliverables.

Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
Verified

D

_________is the process of monitoring and measuring project progress and influencing the plan to account for any discrepancies between planned progress and actual progress.

Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
Verified

A

The laid- back philosophy may be best suited for small projects.

Free
(True/False)
4.8/5
(36)
Correct Answer:
Verified

True

An important issue during the closure process if the _________of the project management methods you have used.

(Short Answer)
4.8/5
(31)

_________is the process of screening the project results to determine whether they conform to relevant quality standards and identifying means to eliminate causes of unsatisfactory results.

(Short Answer)
4.8/5
(42)

All of the following are philosophies of project control EXCEPT:

(Multiple Choice)
4.8/5
(34)

The _________is the ratio of EV to AC.

(Multiple Choice)
5.0/5
(45)

A change control system is a documented process that describes the procedures by which:

(Multiple Choice)
4.8/5
(37)

_________are items or activities that will still need to be addressed but, because of their nature, may need to be addressed by the clients themselves of assigned to a team member to attend after the official project handover.

(Short Answer)
4.8/5
(34)

_________are documented recommendations that minimize the probability of negative consequences to the project.

(Multiple Choice)
4.9/5
(31)

_________is the process of identifying the cause of variance relative to the project baseline and determining whether any corrective action is needed.

(Short Answer)
4.9/5
(34)

Withholding negative information out of fear for negative consequences is known as:

(Multiple Choice)
4.8/5
(34)

_________are documented and authorized guidelines necessary to bring future project performance in conformance with the project management plan.

(Multiple Choice)
4.9/5
(28)

In addition to the philosophy of project control employed, the manager also needs to_________.

(Short Answer)
4.9/5
(41)

Cost control is the process of monitoring cost performance to ensure that only appropriate changes are included in the modified_________.

(Short Answer)
4.7/5
(33)

For large, complex projects, the_________ may be most appropriate.

(Multiple Choice)
4.9/5
(38)

Controlling processes are important factor in all of the following project management knowledge areas EXCEPT_________ management.

(Multiple Choice)
4.8/5
(40)

A _________system is a formal, documented process that describes the procedures for changing the project scope and product scope.

(Short Answer)
4.8/5
(45)

If AC is greater than EV, this means that the project is currently coming in under budget.

(True/False)
4.9/5
(38)

_________is the process of identifying, evaluating, and managing changes that occur from project initiation through project closure.

(Short Answer)
4.8/5
(30)
Showing 1 - 20 of 110
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)