Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis52 Questions
Exam 2: Introduction to Optimization and Linear Programming62 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet88 Questions
Exam 4: Sensitivity Analysis and the Simplex Method72 Questions
Exam 5: Network Modeling72 Questions
Exam 6: Integer Linear Programming72 Questions
Exam 7: Goal Programming and Multiple Objective Optimization59 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization68 Questions
Exam 9: Regression Analysis76 Questions
Exam 10: Discriminant Analysis57 Questions
Exam 11: Time Series Forecasting111 Questions
Exam 12: Introduction to Simulation Using Risk Solver Platform65 Questions
Exam 13: Queuing Theory79 Questions
Exam 14: Decision Analysis102 Questions
Exam 15: Project Management Online61 Questions
Select questions type
What is the latest finish time for activity D in the following diagram? 

(Multiple Choice)
4.9/5
(35)
Non-critical activities are distinguished by the presence of
(Multiple Choice)
4.8/5
(41)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. Identify each path through the network and its expected length.
(Essay)
4.9/5
(33)
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?


(Essay)
4.9/5
(35)
If the following project must be completed by day 18 at minimum cost how do we change the LP model? 

(Multiple Choice)
4.7/5
(37)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?


(Essay)
4.9/5
(35)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.
(Essay)
4.7/5
(40)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E,F 3 16 19 16 19
-Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?

(Multiple Choice)
4.8/5
(37)
If we are employing Activity-On-Arc (AOA) network design, the arcs in the network diagram represent
(Multiple Choice)
4.9/5
(42)
What is the earliest start time for activity D in the following diagram? 

(Multiple Choice)
4.8/5
(37)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E,F 3 16 19 16 19
-Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?

(Multiple Choice)
4.9/5
(39)
The purpose of the forward pass in the Critical Path Method (CPM) technique is to
(Multiple Choice)
4.7/5
(31)
The longest path through a network is comprised of the ____ activities.
(Multiple Choice)
4.9/5
(30)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.
(Essay)
4.7/5
(31)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity E B 2 5 7 5 7 0 7 F Activity F E 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0
(Essay)
4.8/5
(39)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
A B C 1 Activity Description Predlecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity E B 2 5 7 5 7 0 7 F Activity F E 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0
(Essay)
4.9/5
(42)
What are the immediate successors of activity D in this network? 

(Multiple Choice)
4.8/5
(34)
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E,F 3 16 19 16 19
-Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?