What is the latest finish time for activity D in the following diagram? What is the latest finish time for activity D in the following diagram?

(Multiple Choice)
4.9/5
(35)

Non-critical activities are distinguished by the presence of

(Multiple Choice)
4.8/5
(41)

Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F -Refer to Exhibit 15.3. Identify each path through the network and its expected length.

(Essay)
4.9/5
(33)

A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis? A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?

(Essay)
4.9/5
(35)

If the following project must be completed by day 18 at minimum cost how do we change the LP model? If the following project must be completed by day 18 at minimum cost how do we change the LP model?

(Multiple Choice)
4.7/5
(37)

Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity. Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.      -Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts? Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.      -Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts? -Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?

(Essay)
4.9/5
(35)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F -Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.

(Essay)
4.7/5
(40)

Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.  Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}   -Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet? A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E,F 3 16 19 16 19 -Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?

(Multiple Choice)
4.8/5
(37)

If we are employing Activity-On-Arc (AOA) network design, the arcs in the network diagram represent

(Multiple Choice)
4.9/5
(42)

What is the earliest start time for activity D in the following diagram? What is the earliest start time for activity D in the following diagram?

(Multiple Choice)
4.8/5
(37)

Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.  Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}   -Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time? A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E,F 3 16 19 16 19 -Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?

(Multiple Choice)
4.9/5
(39)

A weakness of Gantt charts is that they do not explicitly

(Multiple Choice)
4.8/5
(39)

The purpose of the forward pass in the Critical Path Method (CPM) technique is to

(Multiple Choice)
4.7/5
(31)

The longest path through a network is comprised of the ____ activities.

(Multiple Choice)
4.9/5
(30)

Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F -Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.

(Essay)
4.7/5
(31)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F -Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times? A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity E B 2 5 7 5 7 0 7 F Activity F E 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0

(Essay)
4.8/5
(39)

Which activities are critical in the following diagram? Which activities are critical in the following diagram?

(Multiple Choice)
4.8/5
(35)

Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities: Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F -Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times? A B C 1 Activity Description Predlecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity E B 2 5 7 5 7 0 7 F Activity F E 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0

(Essay)
4.9/5
(42)

What are the immediate successors of activity D in this network? What are the immediate successors of activity D in this network?

(Multiple Choice)
4.8/5
(34)

Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.  Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}   -Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time? A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 3 B Activity B A 3 4 7 4 7 4 C Activity C A 2 4 6 5 7 5 D Activity D ? 7 ? ? ? ? 6 E Activity E D 1 14 15 15 16 7 F Activity F D 2 14 16 14 16 8 G Activity G E,F 3 16 19 16 19 -Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?

(Multiple Choice)
4.7/5
(36)
Showing 21 - 40 of 61