Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis52 Questions
Exam 2: Introduction to Optimization and Linear Programming62 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet88 Questions
Exam 4: Sensitivity Analysis and the Simplex Method72 Questions
Exam 5: Network Modeling72 Questions
Exam 6: Integer Linear Programming72 Questions
Exam 7: Goal Programming and Multiple Objective Optimization59 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization68 Questions
Exam 9: Regression Analysis76 Questions
Exam 10: Discriminant Analysis57 Questions
Exam 11: Time Series Forecasting111 Questions
Exam 12: Introduction to Simulation Using Risk Solver Platform65 Questions
Exam 13: Queuing Theory79 Questions
Exam 14: Decision Analysis102 Questions
Exam 15: Project Management Online61 Questions
Select questions type
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
(Essay)
4.8/5
(37)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity E B 2 5 7 5 7 0 7 F Activity F E 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0
(Essay)
4.8/5
(42)
Which of the following definitions correctly defines the acronym, PERT?
(Multiple Choice)
4.7/5
(34)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. Identify each path through the network and its expected length.
(Essay)
4.9/5
(33)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 5 0 5 0 5 0 3 B Activity B A 3 5 8 10 13 5 4 C Activity C A 4 5 9 5 9 0 5 D Activity D B,C 7 9 16 13 20 4 6 E Activity E C 6 9 15 9 15 0 7 F Activity F E 5 15 20 15 20 0 8 G Activity G D, F 4 20 24 20 24 0
(Essay)
4.7/5
(33)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
A B C 1 Activity Description Predlecessor Time EST EFT LST LFT Slack 2 A Activity A 5 0 5 0 5 0 3 B Activity B A 3 5 8 10 13 5 4 C Activity C A 4 5 9 5 9 0 5 D Activity D B,C 7 9 16 13 20 4 6 E Activity E C 6 9 15 9 15 0 7 F Activity F E 5 15 20 15 20 0 8 G Activity G D, F 4 20 24 20 24 0
(Essay)
4.7/5
(28)
Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT)?
(Multiple Choice)
4.7/5
(39)
There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?
(Multiple Choice)
4.8/5
(43)
Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that
(Multiple Choice)
4.7/5
(38)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 0 3 B Activity B A 3 4 7 4 7 0 4 C Activity C A 2 4 6 5 7 1 5 D Activity D B,C 7 7 14 7 14 0 6 E Activity E D 1 14 15 15 16 1 7 F Activity F D 2 14 16 14 16 0 8 G Activity G E,F 3 16 19 16 19 0
-Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?

(Multiple Choice)
4.9/5
(35)
What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts? 

(Multiple Choice)
4.8/5
(37)
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activties A 1 - B 4 A C 3 B D 3 E 2 B F 4 E G 2 D.F
-Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 1 0 1 0 1 0 3 B Activity B A 4 1 5 1 5 0 4 C Activity C B 3 5 8 5 8 0 5 D Activity D C 3 8 11 8 11 0 6 E Activity E B 2 5 7 5 7 0 7 F Activity F E 4 7 11 7 11 0 8 G Activity G D, F 2 11 13 11 13 0
(Essay)
4.8/5
(49)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?


(Essay)
4.8/5
(26)
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
-Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?


(Short Answer)
4.8/5
(38)
Activity-on-Arc (AOA) networks do not allow multiple arcs with common start and finish nodes. If this must be represented, how is an AOA network modified?