Exam 15: Project Management Online
Exam 1: Introduction to Modeling and Decision Analysis52 Questions
Exam 2: Introduction to Optimization and Linear Programming62 Questions
Exam 3: Modeling and Solving Lp Problems in a Spreadsheet88 Questions
Exam 4: Sensitivity Analysis and the Simplex Method72 Questions
Exam 5: Network Modeling72 Questions
Exam 6: Integer Linear Programming72 Questions
Exam 7: Goal Programming and Multiple Objective Optimization59 Questions
Exam 8: Nonlinear Programming and Evolutionary Optimization68 Questions
Exam 9: Regression Analysis76 Questions
Exam 10: Discriminant Analysis57 Questions
Exam 11: Time Series Forecasting111 Questions
Exam 12: Introduction to Simulation Using Risk Solver Platform65 Questions
Exam 13: Queuing Theory79 Questions
Exam 14: Decision Analysis102 Questions
Exam 15: Project Management Online61 Questions
Select questions type
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 5 0 5 0 5 0 3 B Activity B A 3 5 8 10 13 5 4 C Activity C A 4 5 9 5 9 0 5 D Activity D B,C 7 9 16 13 20 4 6 E Activity E C 6 9 15 9 15 0 7 F Activity F E 5 15 20 15 20 0 8 G Activity G D, F 4 20 24 20 24 0
Free
(Short Answer)
4.8/5
(27)
Correct Answer:
Activities A, C, E, F, and G.
A strength of Gantt charts is that they
Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
C
The purpose of the backward pass in the Critical Path Method (CPM) technique is to
Free
(Multiple Choice)
4.7/5
(40)
Correct Answer:
D
How many paths are there in the following project precedence network? 

(Multiple Choice)
4.7/5
(36)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Activity Predecessor Activities A \@cdots B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,FG
-Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?
(Essay)
4.9/5
(25)
If we are employing Activity-On-Node (AON) network design, the arcs in the network diagram represent
(Multiple Choice)
4.8/5
(39)
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 4 0 4 0 4 0 3 B Activity B A 3 4 7 4 7 0 4 C Activity C A 2 4 6 5 7 1 5 D Activity D B,C 7 7 14 7 14 0 6 E Activity E D 1 14 15 15 16 1 7 F Activity F D 2 14 16 14 16 0 8 G Activity G E,F 3 16 19 16 19 0
-Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?

(Multiple Choice)
4.9/5
(33)
What are the immediate predecessors of activity D in this network? 

(Multiple Choice)
4.8/5
(36)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
(Essay)
4.9/5
(41)
What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day? 

(Multiple Choice)
4.8/5
(38)
In a PERT network the time required to complete a path is a(n)
(Multiple Choice)
4.7/5
(40)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Activity Predecessor Activities A \@cdots B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,FG
-Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.
Activity Predecessor Activities Immediate Predecessors A \@cdots -- B A A C A,B B D A,B B E A,B,C F A,B,C G A, B,C,D H A,B,D I A,B,C,D.FG
(Essay)
4.9/5
(41)
Which of the following correctly describes the focus of the Critical Path Method (CPM)?
(Multiple Choice)
4.8/5
(30)
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis? 

(Multiple Choice)
4.9/5
(29)
What is the formula for the earliest finish time for activity i?
(Multiple Choice)
4.7/5
(33)
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Activity Days Required Predecessar Activities A 5 - B 3 A C 4 A D 7 B,C E 6 C F 5 E G 4 D. F
-Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
A B C 1 Activity Description Predecessor Time EST EFT LST LFT Slack 2 A Activity A 5 0 5 0 5 0 3 B Activity B A 3 5 8 10 13 5 4 C Activity C A 4 5 9 5 9 0 5 D Activity D B,C 7 9 16 13 20 4 6 E Activity E C 6 9 15 9 15 0 7 F Activity F E 5 15 20 15 20 0 8 G Activity G D, F 4 20 24 20 24 0
(Essay)
4.9/5
(34)
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Activity Predecessor Activities A \@cdots B A C A,B D A,B E A,B,C F A,B,C G A,B,C,D H A,B,D I A,B,C,D,FG
-Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
(Essay)
4.8/5
(28)
Showing 1 - 20 of 61
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)