Exam 4: Material Requirements Planning
Exam 1: Introduction to Materials Management30 Questions
Exam 2: Production Planning System31 Questions
Exam 3: Master Scheduling25 Questions
Exam 4: Material Requirements Planning41 Questions
Exam 5: Capacity Management23 Questions
Exam 6: Production Activity Control35 Questions
Exam 7: Purchasing38 Questions
Exam 8: Forecasting27 Questions
Exam 9: Inventory Fundamentals27 Questions
Exam 10: Order Quantities25 Questions
Exam 11: Independent Demand Ordering Systems40 Questions
Exam 12: Physical Inventory and Warehouse Management31 Questions
Exam 13: Physical Distribution42 Questions
Exam 14: Products and Processes30 Questions
Exam 15: Lean Production27 Questions
Exam 16: Total Quality Management36 Questions
Select questions type
Which of the following statements is best?
Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
E
Which of the following comes directly from external customers?
Free
(Multiple Choice)
4.9/5
(41)
Correct Answer:
B
In the product structure diagram below item A has _ demand and item D has
Demand.


Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
D
A set of priority planning techniques for planning component items below the end item level is called:
(Multiple Choice)
4.8/5
(38)
Which of the following represents a major difference between a scheduled receipt and a firm planned order?
(Multiple Choice)
4.9/5
(37)
Service parts experience which of the following types of demand?
(Multiple Choice)
4.8/5
(30)
Use the following MRP record and your calculations to answer the following two questions. The component has an order quantity of 100, a safety stock of ten, and a lead time of one period. Complete the following MRP record.
Week 1 2 3 4 Gross requirements 25 80 20 80 Scheduled receipts 100 Projected available 30 Net requirements Planned order receipt Planned order release
-Complete the above MRP record. Which of the following statements is correct?
(Multiple Choice)
4.9/5
(35)
Use the following MRP record and your calculations to answer the following two questions. The component has an order quantity of 100, a safety stock of ten, and a lead time of one period. Complete the following MRP record.
Week 1 2 3 4 Gross requirements 25 80 20 80 Scheduled receipts 100 Projected available 30 Net requirements Planned order receipt Planned order release
-The projected available in period four is:
(Multiple Choice)
4.8/5
(34)
A multi-level bill of material:
I. Reflects the way the product will be manufactured.
II. Is produced by the purchasing department.
III. Is a parts list only and does not contain subassemblies.
(Multiple Choice)
4.9/5
(34)
Which of the following statements is best regarding part numbering systems?
(Multiple Choice)
4.9/5
(41)
In the following product trees the low level code of item D is:


(Multiple Choice)
4.9/5
(39)
The following two questions use the information in this MRP record. The lead time is 3 weeks.
Week 1 2 3 4 5 Gross requirements 60 50 60 70 20 Scheduled receipts 100 Projected available 40 90 30 40 Net requirements Planned order receipt Planned order release 100
-The net requirement for week four is:
(Multiple Choice)
4.8/5
(28)
The ability to relate the demand for an item shown on an MRP record back to the particular parent causing the demand is called:
(Multiple Choice)
5.0/5
(38)
Showing 1 - 20 of 41