Exam 3: Master Scheduling
Exam 1: Introduction to Materials Management30 Questions
Exam 2: Production Planning System31 Questions
Exam 3: Master Scheduling25 Questions
Exam 4: Material Requirements Planning41 Questions
Exam 5: Capacity Management23 Questions
Exam 6: Production Activity Control35 Questions
Exam 7: Purchasing38 Questions
Exam 8: Forecasting27 Questions
Exam 9: Inventory Fundamentals27 Questions
Exam 10: Order Quantities25 Questions
Exam 11: Independent Demand Ordering Systems40 Questions
Exam 12: Physical Inventory and Warehouse Management31 Questions
Exam 13: Physical Distribution42 Questions
Exam 14: Products and Processes30 Questions
Exam 15: Lean Production27 Questions
Exam 16: Total Quality Management36 Questions
Select questions type
The MPS is constrained by:
I. The availability of material.
II. Available capacity.
III. Inventory policies.
IV. Production plan.
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
A
Which of the following modules follows the Sales and Operations Plan?
Free
(Multiple Choice)
4.7/5
(40)
Correct Answer:
C
In an assemble-to-order company, at which level should master scheduling take place?
Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
A
Shifting customer design decisions as far down the supply chain as possible is typically called which of the following?
(Multiple Choice)
4.8/5
(39)
The final assembly schedule as different from the master schedule is primarily used:
(Multiple Choice)
4.7/5
(25)
Given the following table, calculate the ATP. There are 50 units on hand.
Week 1 2 3 4 5 Customer orders 20 20 15 30 10 Scheduled receipts 50
ATP
(Multiple Choice)
4.8/5
(36)
Which of the following is NOT an input to the master production schedule?
(Multiple Choice)
4.8/5
(33)
Which of the following is the term applied to a master schedule for a purchased item?
(Multiple Choice)
4.9/5
(39)
Which of the following is true concerning the demand time fence?
(Multiple Choice)
4.9/5
(42)
If there are customer orders the projected available is based on:
(Multiple Choice)
4.9/5
(35)
Given the following data, complete the table. There are 30 on hand. Order quantity is 60 units.
Week 1 2 3 4 Forecast 20 30 50 20
Projected available
Scheduled receipts
(Multiple Choice)
4.9/5
(38)
Which of the following statements is best regarding the master production schedule?
(Multiple Choice)
4.9/5
(36)
The information needed to develop a master production schedule will be obtained from:
(Multiple Choice)
5.0/5
(39)
A customer requests a new order in a period where there is inadequate material available in the available-to-promise (ATP) for that period, and the period is within the planning time fence. Which of the following is the best first course of action to take in such a situation?
(Multiple Choice)
4.8/5
(37)
Which of the following are objectives of an MPS?
I. Maintain the desired level of customer service.
II. Keep the sales department happy.
III. Make the best use of material, labor and equipment.
IV. Maintain inventory investment as required.
(Multiple Choice)
4.8/5
(31)
Which of the following is (are) true about time fences in a master production schedule system?
I. Changes far out in the planning horizon can be made with little or no cost to manufacturing.
II. In the "frozen zone," capacity and materials are committed to specific orders.
III. Changes in the near future on the planning horizon are less costly to make than changes far out.
(Multiple Choice)
4.9/5
(39)
The time span for which the master schedule extends is called the:
(Multiple Choice)
4.7/5
(28)
The MPS is a vital link the production planning system because it: I. Keeps priorities valid.
II) Forms the basis for determining the capacity needed.
III) Is input to the material requirements plan.
IV) Is input to the production plan.
(Multiple Choice)
4.8/5
(36)
Showing 1 - 20 of 25
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)