Exam 5: Capacity Management
Exam 1: Introduction to Materials Management30 Questions
Exam 2: Production Planning System31 Questions
Exam 3: Master Scheduling25 Questions
Exam 4: Material Requirements Planning41 Questions
Exam 5: Capacity Management23 Questions
Exam 6: Production Activity Control35 Questions
Exam 7: Purchasing38 Questions
Exam 8: Forecasting27 Questions
Exam 9: Inventory Fundamentals27 Questions
Exam 10: Order Quantities25 Questions
Exam 11: Independent Demand Ordering Systems40 Questions
Exam 12: Physical Inventory and Warehouse Management31 Questions
Exam 13: Physical Distribution42 Questions
Exam 14: Products and Processes30 Questions
Exam 15: Lean Production27 Questions
Exam 16: Total Quality Management36 Questions
Select questions type
Which of the following is the best statement?
Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
D
The difference between backward scheduling and forward scheduling is which of the following?
Free
(Multiple Choice)
4.7/5
(40)
Correct Answer:
A
A shows the capacity required at each work center based on planned and released orders for each time period of the plan.
Free
(Multiple Choice)
4.9/5
(29)
Correct Answer:
B
The percentage of time the work center is active compared to the available time is called:
(Multiple Choice)
4.9/5
(30)
Rated capacity is calculated taking into account work center _ and .
I. historical data
II. utilization
III. efficiency
(Multiple Choice)
4.8/5
(42)
is responsible for capacity planning at the master production schedule level and at the material requirements planning level:
I. Resource planning.
II. Rough-cut capacity planning.
III. Capacity requirements planning.
(Multiple Choice)
4.8/5
(35)
In one week a work center produces 130 standard hours of work. The hours scheduled are
120, and 105 hours are actually worked. The utilization is:
(Multiple Choice)
4.9/5
(29)
Over the previous three weeks a work center produced 36, 43, and 35 standard hours of work. What is the demonstrated capacity?
(Multiple Choice)
4.9/5
(34)
A work center consists of 2 machines working 8 hours a day and 5 days a week.
Historically, utilization has been 80% and the efficiency 90%. The effective capacity, to the nearest hour, would be:
(Multiple Choice)
4.9/5
(39)
is responsible for determining the capacity required and methods of making the capacity available.
(Multiple Choice)
4.8/5
(31)
A report that shows the future capacity requirements based on released and planned orders for each time period of the plan is called:
(Multiple Choice)
4.8/5
(25)
The capacity available with no regard for downtime, utilization and efficiency is:
(Multiple Choice)
5.0/5
(34)
The ratio of standard hours of work produced to hours actually worked is called:
(Multiple Choice)
4.8/5
(38)
Information on the standard times for an operation will be found in:
(Multiple Choice)
4.9/5
(40)
The available capacity will be influenced by: I. Product specification.
II) Product mix.
III) Work effort.
IV) Units of measurement
(Multiple Choice)
4.9/5
(36)
are generated by the priority planning system and involve the translation of the priorities, generally given in units of product or some common unit, into hours of work required at each work center in each time period:
(Multiple Choice)
4.8/5
(27)
Which of the following is NOT an input needed in capacity requirements planning?
(Multiple Choice)
4.8/5
(26)
One hundred units of part A are to be processed on a work center. The setup time is 2 hours and the run time per piece is 10 minutes. The total standard time will be: