Exam 6: Production Activity Control

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A scheduling system that assumes the required capacity will always be available is called:

Free
(Multiple Choice)
4.7/5
(30)
Correct Answer:
Verified

C

Operation overlapping means:

Free
(Multiple Choice)
4.9/5
(34)
Correct Answer:
Verified

C

The planned backlog was:

Free
(Multiple Choice)
4.7/5
(30)
Correct Answer:
Verified

A

The following information is to be used in this and the next question. For the last week a work center had a planned input of 40 standard hours and an actual input of 36 standard hours. The planned output was 40, the actual output 42 standard hours and the beginning backlog was 30 hours. The cumulative input variance was:

(Multiple Choice)
4.8/5
(29)

Which of the following statements is best?

(Multiple Choice)
4.9/5
(27)

A production environment in which each unit or a small group of units is managed by a process created especially for that purpose is called

(Multiple Choice)
4.7/5
(33)

If the previous backlog was 20 units, the planned input was 25 units and the planned output was 30 units the planned backlog would be:

(Multiple Choice)
4.8/5
(35)

The shows the total standard time required to produce one end product in each work center required for its manufacture:

(Multiple Choice)
4.9/5
(34)

Which of the following dispatching rules ignore due dates?

(Multiple Choice)
4.8/5
(30)

A scheduling system that assumes the required capacity will NOT always be available is called:

(Multiple Choice)
4.8/5
(43)

Which of the following are characteristics of intermittent manufacturing? I. Work centers are arranged according to the routing. II. Work centers are dedicated to producing a limited range of similar products. III. Work flow through the shop is not constant. IV. Throughput times are generally high.

(Multiple Choice)
4.8/5
(40)

Which of the following statements is best?

(Multiple Choice)
4.8/5
(39)

Which of the following are methods of reducing manufacturing lead time? I. Subcontracting II. Forward scheduling III. Operation overlapping IV. Operation splitting

(Multiple Choice)
4.7/5
(34)

A shop order for 1000 pieces is to be processed on work station 123. The setup time is 4 hours and the run time per piece is .08 hours. What is the required capacity on this work center in standard hours?

(Multiple Choice)
4.9/5
(32)

Which of the following statements is best?

(Multiple Choice)
4.8/5
(36)

Which of the following is concerned with very short-term detailed planning of the flow of orders through manufacturing?

(Multiple Choice)
4.9/5
(39)

In a drum-buffer-rope scheduling system, the "drum" represents which of the following?

(Multiple Choice)
5.0/5
(31)

A scheduling system in which the last operation on a routing is scheduled first and for completion on the due date is called:

(Multiple Choice)
4.8/5
(41)

Which of the following statements is best?

(Multiple Choice)
4.7/5
(35)

Given the following data, which job(s) will be late if the shortest process time sequencing rule is used? Today is day 100. Job Process Time Due Date A 4 104 B 1 106 C 5 109

(Multiple Choice)
4.8/5
(40)
Showing 1 - 20 of 35