Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

(Multiple Choice)
4.9/5
(43)

A Gantt chart is often the name for the network diagram tool for planning and scheduling.

(True/False)
4.8/5
(34)

Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.

(Multiple Choice)
4.9/5
(27)