Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
4.8/5
(39)

When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a person who

(Multiple Choice)
4.9/5
(44)

Latest finish time (LF) is the latest time by which a specific activity must be

(Multiple Choice)
4.7/5
(43)

The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.

(True/False)
4.8/5
(35)

The project team can progressively elaborate the estimated durations as more information is known or becomes clear to allow for more accurate estimated durations.

(True/False)
4.9/5
(33)

It is necessary to monitor the progress to ensure that everything is going according to the plan.

(True/False)
4.8/5
(31)

Each organisation or subcontractor responsible for a group or type of activities should always designate an inexperienced individual to estimate the durations for all the activities for which the organisation or subcontractor is responsible.

(True/False)
4.7/5
(47)

Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.

(Multiple Choice)
4.9/5
(30)

The project control process must occur regularly throughout the project and include all of the following except

(Multiple Choice)
4.7/5
(45)

Padding estimates with the vision of becoming a hero when the activities are completed in less time than estimated is not a good practice.

(True/False)
4.9/5
(36)

The ES and EF times are determined by calculating forward, that is, by

(Multiple Choice)
4.8/5
(44)

A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that

(Multiple Choice)
4.8/5
(41)

The estimated activity resources will also be used later for estimating activity costs and determining the project budget.

(True/False)
4.8/5
(25)

When considering the availability of resources, it may be necessary to make some assumptions, such as

(Multiple Choice)
4.9/5
(45)

At the beginning of every project, it is possible to estimate the durations for all activities with a high level of confidence regarding their accuracy.

(True/False)
4.7/5
(46)

With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:

(Multiple Choice)
4.9/5
(37)

Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then

(Multiple Choice)
4.8/5
(44)

The estimated duration should be aggressive, yet unrealistic.

(True/False)
4.8/5
(43)

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.How much slack does the project have?

(Multiple Choice)
4.9/5
(36)

In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to

(Multiple Choice)
4.9/5
(34)
Showing 41 - 60 of 83
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)