Exam 5: Developing the Schedule
Exam 1: Project Management Concepts78 Questions
Exam 2: Identifying and Selecting Projects69 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility and Activity Sequence115 Questions
Exam 5: Developing the Schedule83 Questions
Exam 6: Resource Utilisation22 Questions
Exam 7: Determining Costs, Budget and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project41 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organisational Structures65 Questions
Select questions type
Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
(Multiple Choice)
4.8/5
(39)
When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a person who
(Multiple Choice)
4.9/5
(44)
Latest finish time (LF) is the latest time by which a specific activity must be
(Multiple Choice)
4.7/5
(43)
The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.
(True/False)
4.8/5
(35)
The project team can progressively elaborate the estimated durations as more information is known or becomes clear to allow for more accurate estimated durations.
(True/False)
4.9/5
(33)
It is necessary to monitor the progress to ensure that everything is going according to the plan.
(True/False)
4.8/5
(31)
Each organisation or subcontractor responsible for a group or type of activities should always designate an inexperienced individual to estimate the durations for all the activities for which the organisation or subcontractor is responsible.
(True/False)
4.7/5
(47)
Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
(Multiple Choice)
4.9/5
(30)
The project control process must occur regularly throughout the project and include all of the following except
(Multiple Choice)
4.7/5
(45)
Padding estimates with the vision of becoming a hero when the activities are completed in less time than estimated is not a good practice.
(True/False)
4.9/5
(36)
The ES and EF times are determined by calculating forward, that is, by
(Multiple Choice)
4.8/5
(44)
A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
(Multiple Choice)
4.8/5
(41)
The estimated activity resources will also be used later for estimating activity costs and determining the project budget.
(True/False)
4.8/5
(25)
When considering the availability of resources, it may be necessary to make some assumptions, such as
(Multiple Choice)
4.9/5
(45)
At the beginning of every project, it is possible to estimate the durations for all activities with a high level of confidence regarding their accuracy.
(True/False)
4.7/5
(46)
With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible to use three time estimates:
(Multiple Choice)
4.9/5
(37)
Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then
(Multiple Choice)
4.8/5
(44)
The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.How much slack does the project have?
(Multiple Choice)
4.9/5
(36)
In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to
(Multiple Choice)
4.9/5
(34)
Showing 41 - 60 of 83
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)