Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Having the person who will be responsible for performing a specific activity estimate the duration for that activity from that person and that may be introduced by having one person estimate the durations for all of the activities.

(Multiple Choice)
4.9/5
(32)

The contractor may not want to commit to completing the project by a specific date until the customer has approved the contract.

(True/False)
4.8/5
(43)

The scrum master is as a project manager in that he responsibility for the people on the development team.

(Multiple Choice)
4.8/5
(35)

Total slack is calculated for each of the activities by finding the difference between

(Multiple Choice)
4.9/5
(36)

Throughout a project, changes may occur that have an impact on the schedule.

(True/False)
4.8/5
(45)

When estimating resources for activities to estimate the activity's duration, the

(Multiple Choice)
4.8/5
(33)

People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,

(Multiple Choice)
4.9/5
(34)

Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of

(Multiple Choice)
4.9/5
(34)

Playing the game of inflating estimated durations in anticipation of the project manager negotiating shorter durations is good practice.

(True/False)
4.9/5
(38)

The development team develops, delivers, and demonstrates during a sprint.

(Multiple Choice)
4.7/5
(36)

A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.

(True/False)
4.9/5
(28)

The amount of slack should determine the priority with which these concentrated efforts are applied.

(True/False)
4.9/5
(33)

Earliest start time (ES) is the earliest time at which a specific activity can begin

(Multiple Choice)
4.8/5
(32)

For large projects that involve several hundred people performing various activities over several years, it is practical to have each person estimate activity durations at the beginning of the project.

(True/False)
4.9/5
(36)

Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated

(Multiple Choice)
5.0/5
(38)

The project control process involves all of the following except

(Multiple Choice)
4.8/5
(39)

The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity.

(True/False)
4.8/5
(49)

If the planned corrective actions do not result in an acceptable schedule, then

(Multiple Choice)
4.9/5
(36)

Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

(Multiple Choice)
4.8/5
(33)

The earliest start time for a specific activity must be the latest of all the earliest finish times of all the activities leading directly into that specific activity.

(Multiple Choice)
4.9/5
(41)
Showing 61 - 80 of 83