Exam 4: Defining Scope, Quality, Responsibility and Activity Sequence
Exam 1: Project Management Concepts78 Questions
Exam 2: Identifying and Selecting Projects69 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility and Activity Sequence115 Questions
Exam 5: Developing the Schedule83 Questions
Exam 6: Resource Utilisation22 Questions
Exam 7: Determining Costs, Budget and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project41 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organisational Structures65 Questions
Select questions type
It is important to document the detailed requirements in the __in order to establish a clear understanding with the sponsor or customer.
(Multiple Choice)
4.8/5
(42)
The responsibility assignment matrix may use a P to designate responsibility and an S to indicate responsibility for a specific work item.
(Multiple Choice)
4.8/5
(31)
The major work elements defined in the statement of work section along with the detailed list of deliverables provide the basis for creating a
(Multiple Choice)
4.8/5
(35)
The work package includes all of the specific work activities that need to be performed to produce the deliverable associated with that work package.
(True/False)
4.9/5
(35)
contains a small number of higher-level activities rather than a large number of detailed activities.
(Multiple Choice)
4.8/5
(38)
The WBS usually indicates the organisation or individual assigned responsibility for performance and completion of each work item.
(True/False)
4.7/5
(41)
For large or complex projects, it may be difficult for one individual to determine all the work elements to include in the work breakdown structure.
(True/False)
4.7/5
(30)
A responsibility assignment matrix defines who will be paid for the work.
(True/False)
4.9/5
(45)
An activity, also referred to as a task, is a defined piece of work that consumes effort by people and not necessarily time.
(True/False)
4.8/5
(42)
Using the work breakdown structure, the individual or team responsible for each work package must next define all the specific activities that need to be performed to produce the end item or deliverable for the work package.
(True/False)
4.8/5
(34)
The contractor or project team needs to gain agreement from on the project scope document.
(Multiple Choice)
4.7/5
(36)
To draw a , start by drawing the activities in boxes in their logical sequence and connecting them with arrows to show the required dependent relationships, as the project should be performed from start to completion.
(Multiple Choice)
4.8/5
(29)
Once the project scope document has been prepared and agreed on, the next step in the planning phase is to
(Multiple Choice)
4.8/5
(32)
The project manager should involve every project member in developing the WBS to have special expertise, knowledge, or experience that will help develop a more comprehensive and complete WBS.
(True/False)
4.7/5
(35)
is a structured approach for organising all the project work and deliverables into logical groupings and subdividing them into more manageable components to help ensure that all the work and deliverables to complete the project are identified and included in the baseline project plan.
(Multiple Choice)
4.8/5
(29)
A detailed description of each deliverable should be stated to provide a basis for agreement between the project team or contractor and the customer of
(Multiple Choice)
4.9/5
(35)
A detailed description of each deliverable will help to manage stakeholder expectations.
(True/False)
4.8/5
(39)
Showing 61 - 80 of 115
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)