Exam 3: Developing Project Proposals
Exam 1: Project Management Concepts78 Questions
Exam 2: Identifying and Selecting Projects69 Questions
Exam 3: Developing Project Proposals112 Questions
Exam 4: Defining Scope, Quality, Responsibility and Activity Sequence115 Questions
Exam 5: Developing the Schedule83 Questions
Exam 6: Resource Utilisation22 Questions
Exam 7: Determining Costs, Budget and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project41 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation124 Questions
Exam 13: Project Management Organisational Structures65 Questions
Select questions type
As soon as a contractor finds out it is the winner, it can start working on the project.
(True/False)
4.9/5
(46)
The contractor should state its understanding of the customer's need
(Multiple Choice)
4.9/5
(36)
If a customer has stated the budget in the RFP, the customer might reject proposals that have cost estimates greater than the budget without further review of the proposal.
(True/False)
4.8/5
(34)
A contractor that is entering a similar but new field should plan a smaller profit to increase chances of winning the project.
(True/False)
4.8/5
(39)
Indirect costs of doing business are included in proposals where the customer permits the charging of indirect costs.
(True/False)
4.9/5
(33)
The total Rand value approach is the ratio of the total Rand value of proposals that the contractor won as a percentage of the total Rand value of all the proposals the contractor submitted to various customers during a specific time period.
(True/False)
4.9/5
(38)
It is advisable to build relationship with in a client or partner organisation.
(Multiple Choice)
4.9/5
(38)
Waiting to develop a proposal until an RFP is announced is important to be sure all the information is available.
(True/False)
4.9/5
(30)
Sleeping on a contradictory issue and providing a thoughtful answer the next day
(Multiple Choice)
4.9/5
(33)
A contractor should only respond to RFPs if they have the required resources already on their staff.
(True/False)
4.8/5
(33)
A contractor should make a no-bid decision for a project that would not be consistent the contractor's business mission.
(True/False)
4.7/5
(33)
The type of contract where the customer and the contractor agree on a price for the proposed work is
(Multiple Choice)
4.9/5
(34)
Including complicated graphics in a proposal demonstrates a contractor's advanced skill and shows specific technical expertise.
(True/False)
4.8/5
(44)
Historical data can be used to guide estimating costs for a proposed project.
(True/False)
4.9/5
(48)
The reputation of the company that announced the RFP should be evaluated as a factor as well as the reputation of the contractor when making a bid or no-bid decision.
(True/False)
4.9/5
(33)
Taking credit for outcomes that others have achieved is a way to build yourself for others to respect you.
(True/False)
4.7/5
(38)
Fixed-price contracts are most appropriate for projects that
(Multiple Choice)
4.8/5
(48)
Showing 41 - 60 of 112
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)