Exam 3: Managing the Information Systems Project

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A controlled process of initiating,planning,executing,and closing down a project best defines:

(Multiple Choice)
4.8/5
(31)

Identify the common activities and skills of a project manager.

(Essay)
4.9/5
(36)

Slack time is equal to:

(Multiple Choice)
4.8/5
(34)

Gantt charts visually show the time overlap of tasks whereas a network diagram does not show time overlap but does show which tasks could be done in parallel.

(True/False)
4.8/5
(32)

A work method is any person,group of people,piece of equipment,or material used in accomplishing an activity.

(True/False)
4.9/5
(34)

Which of the following is not a project closedown phase?

(Multiple Choice)
4.7/5
(30)

________ is a technique that uses optimistic,pessimistic,and realistic time estimates to calculate the expected time for a particular task.

(Short Answer)
4.8/5
(30)

Addressing hard problems first does not mitigate risk.

(True/False)
4.8/5
(34)

Which of the following project management activities is associated with project initiation?

(Multiple Choice)
4.8/5
(41)

Establishing a relationship with the customer is a project initiation activity.

(True/False)
4.7/5
(38)

Managing conflict within a project team to assure that conflict is not too high or too low describes the ________ project manager activity.

(Short Answer)
4.9/5
(45)

A systems development project may be undertaken to take advantage of business opportunities or to solve business problems.

(True/False)
4.9/5
(38)

Experienced OOSAD project managers typically use from six to nine iterations when designing and constructing a system.

(True/False)
4.9/5
(33)

A ________ determines if the proposed information system makes sense for the organization from an economic and operational standpoint.

(Short Answer)
4.9/5
(28)

In order to manage the project as a series of iterations,the project manager must subdivide the project into a set of components.

(True/False)
4.9/5
(45)

A ________ is the shortest time in which a project can be completed.

(Short Answer)
4.8/5
(38)

________ is the final phase of the project management process that focuses on ending the project.

(Short Answer)
4.8/5
(21)

Referring to OOSAD,in order to manage the project as a series of iterations,the project manager must subdivide the overall system into a set of ________.

(Short Answer)
4.9/5
(34)

An activity on the critical path will have a slack time of 1.

(True/False)
4.9/5
(32)

A ________ is an end product in a phase of the SDLC.

(Short Answer)
4.8/5
(38)
Showing 81 - 100 of 159
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)