Exam 3: Managing the Information Systems Project
Exam 1: The Systems Development Environment155 Questions
Exam 2: The Origins of Software124 Questions
Exam 3: Managing the Information Systems Project159 Questions
Exam 4: Identifying and Selecting Systems Development Projects139 Questions
Exam 5: Initiating and Planning Systems Development Projects134 Questions
Exam 6: Determining System Requirements133 Questions
Exam 7: Structuring System Process Requirements182 Questions
Exam 8: Structuring System Data Requirements122 Questions
Exam 9: Designing Databases134 Questions
Exam 10: Designing Forms and Reports135 Questions
Exam 11: Designing Interfaces and Dialogues134 Questions
Exam 12: Designing Distributed and Internet Systems135 Questions
Exam 13: System Implementation130 Questions
Exam 14: Maintaining Information Systems136 Questions
Exam 15: Object-Oriented Analysis and Design: Use Cases38 Questions
Exam 16: Object-Oriented Analysis and Design: Activity Diagrams9 Questions
Exam 17: Object-Oriented Analysis and Design: Sequence Diagrams30 Questions
Exam 18: Business Process Modeling20 Questions
Exam 19: Objected-Oriented Analysis and Design: Object Modeling-Class Diagrams27 Questions
Select questions type
Project time estimates for task completion and overall system quality are significantly influenced by the assignment of people to tasks.
(True/False)
4.9/5
(30)
Which of the following states correctly the formality and use of a project workbook?
(Multiple Choice)
4.8/5
(35)
In order to determine the resources required for project completion,an organization should analyze the project's scope and determine the project's probability of successful completion.
(True/False)
4.9/5
(31)
Project planning is the first phase of the project management process in which activities are performed to assess the size,scope,and complexity of the project and to establish procedures to support later project activities.
(True/False)
4.8/5
(33)
What would be the estimated time for completion if time estimates for installation are as follows: optimistic = 1 week;pessimistic = 1 week;realistic = 1 week?
(Multiple Choice)
4.8/5
(26)
The amount of time that an activity can be delayed without delaying the project refers to:
(Multiple Choice)
4.7/5
(36)
Which of the following is true regarding Gantt chart construction?
(Multiple Choice)
4.8/5
(35)
________ are any person,group of people,piece of equipment,or material used in accomplishing an activity.
(Short Answer)
4.8/5
(33)
In OOSAD,during inception the primary focus is analysis,during elaboration the primary focus is design,during construction the primary focus is making the system truly operational,and during transition the primary focus is on implementation.
(True/False)
4.9/5
(46)
Another characteristic of the OOSAD approach is that it tackles the ________ first.
(Short Answer)
4.8/5
(42)
During which of the following activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?
(Multiple Choice)
4.8/5
(35)
Skills that include interpreting system requests and specifications,site preparation and user training,and contact point for customers best represent:
(Multiple Choice)
4.9/5
(38)
Indicating when and how written and oral reports will be provided by the team,how team members will coordinate work,what messages will be sent to announce the project to interested parties,and what kinds of information will be shared with vendors and external contractors involved with the project describes:
(Multiple Choice)
4.8/5
(34)
The third phase of the project management process in which the plans created in the prior phases are put into action is:
(Multiple Choice)
4.9/5
(39)
A major disadvantage of the network diagram is its inability to represent completion times and show interrelationships between activities.
(True/False)
4.9/5
(27)
One outcome of defining the overall system as a collection of components is the likelihood that the components constructed earlier in the project will require greater rework than those developed later in the project.
(True/False)
4.8/5
(25)
The Project Scope Statement provides a detailed estimate of the project's tasks and resource requirements.
(True/False)
4.9/5
(33)
If an activity's optimistic time is 3 months,its realistic time is 5 months,and its pessimistic time is 10 months,then its estimated time would be 5.5 months.
(True/False)
4.8/5
(41)