Exam 3: Managing the Information Systems Project
Exam 1: The Systems Development Environment155 Questions
Exam 2: The Origins of Software124 Questions
Exam 3: Managing the Information Systems Project159 Questions
Exam 4: Identifying and Selecting Systems Development Projects139 Questions
Exam 5: Initiating and Planning Systems Development Projects134 Questions
Exam 6: Determining System Requirements133 Questions
Exam 7: Structuring System Process Requirements182 Questions
Exam 8: Structuring System Data Requirements122 Questions
Exam 9: Designing Databases134 Questions
Exam 10: Designing Forms and Reports135 Questions
Exam 11: Designing Interfaces and Dialogues134 Questions
Exam 12: Designing Distributed and Internet Systems135 Questions
Exam 13: System Implementation130 Questions
Exam 14: Maintaining Information Systems136 Questions
Exam 15: Object-Oriented Analysis and Design: Use Cases38 Questions
Exam 16: Object-Oriented Analysis and Design: Activity Diagrams9 Questions
Exam 17: Object-Oriented Analysis and Design: Sequence Diagrams30 Questions
Exam 18: Business Process Modeling20 Questions
Exam 19: Objected-Oriented Analysis and Design: Object Modeling-Class Diagrams27 Questions
Select questions type
What would be the estimated time for completion if the time estimates for report design are as follows: optimistic = 3 weeks;pessimistic = 9 weeks;realistic = 6 weeks?
(Multiple Choice)
5.0/5
(34)
With OOAD project management,during each iteration all systems development lifecycle activities are performed.
(True/False)
4.8/5
(33)
A planned undertaking of related activities to reach an objective that has a beginning and an end best defines:
(Multiple Choice)
4.9/5
(31)
A Project Scope Statement is developed during the project execution phase.
(True/False)
4.9/5
(35)
The focus of closing the customer contract activity is to ensure that all contractual terms of the project have been met.
(True/False)
4.8/5
(22)
Managing conflict within a project team to assure that conflict is not too high or too low best defines which of the following project manager activities:
(Multiple Choice)
4.9/5
(39)
Briefly explain the process of managing an information systems project.
(Essay)
4.8/5
(32)
________ is a scheduling technique whose order and duration of a sequence of task activities directly affect the completion date of a project.
(Short Answer)
4.8/5
(28)
Defining the necessary activities required to organize the initiation team while they are working to define the scope of the project is the focus of which of the following activities?
(Multiple Choice)
5.0/5
(31)
Automated tools available to help you manage a development project are referred to as:
(Multiple Choice)
4.8/5
(38)
What would be the estimated time for completion if time estimates for programming are as follows: optimistic = 4 weeks;pessimistic = 6 weeks;realistic = 5 weeks?
(Multiple Choice)
4.8/5
(25)
Within the context of the SDLC,project closedown occurs when the design phase is completed.
(True/False)
4.8/5
(40)
A slipped completion date for an activity may initiate a change to the Baseline Project Plan.
(True/False)
4.7/5
(27)
Rework is not normally part of an OOAD project and one should be overly concerned when this happens.
(True/False)
4.8/5
(37)
If an activity's optimistic time is 4 weeks,its realistic time is 6 weeks,and its pessimistic time is 8 weeks,then its estimated time would be 6 weeks.
(True/False)
4.7/5
(35)
The project workbook serves as a repository for all project correspondence,inputs,outputs,deliverables,procedures,and standards established by the project team.
(True/False)
4.8/5
(37)
Managing the project team for effective team performance describes the ________ project manager activity.
(Short Answer)
4.8/5
(27)
Creating a work breakdown structure requires that you decompose phases into activities and activities into specific tasks.
(True/False)
4.7/5
(23)
Showing 21 - 40 of 159
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)