Exam 3: The Project Management Process Groups: a Case Study

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following project parameters would be compatible with the use of the agile approach?

(Multiple Choice)
4.9/5
(44)

The project time management knowledge area maps to the _____ process group through the activity of schedule control.

(Multiple Choice)
4.8/5
(34)

_____ is a project management methodology that defines 45 separate subprocesses and organizes these into eight process groups.

(Short Answer)
4.9/5
(29)

The kick-off meeting is always held before the business case and project charter are completed.

(True/False)
4.8/5
(36)

The project scope management knowledge area maps to the _____ process group through the activities of scope validation and scope control.

(Multiple Choice)
4.8/5
(38)

The DMAIC (Define, Measure, Analyze, Improve, and Control) methodology of the Six Sigma projects, is used to improve an existing business process.

(True/False)
4.8/5
(29)

Which of the following is a pre-initiation task?

(Multiple Choice)
4.8/5
(36)

Which of the following is a planning process associated with project scope management?

(Multiple Choice)
4.9/5
(43)

The output of the stakeholder management strategy results is a project charter.

(True/False)
4.9/5
(33)

The improvement of the product and process in the Scrum method is discussed at the _____.

(Multiple Choice)
4.7/5
(32)

Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in _____ processes.

(Multiple Choice)
4.9/5
(29)

Project initiation involves taking the actions necessary to ensure that activities in the project plan are completed.

(True/False)
4.9/5
(23)

What is a work breakdown structure?

(Essay)
4.9/5
(29)

Initiating and closing tasks are usually the longest and require the most amount of resources and time.

(True/False)
4.8/5
(48)

Initiating processes take place during each phase of a project.

(True/False)
4.9/5
(33)

Agile methods comprise of 45 subprocesses which are organized into eight process groups.

(True/False)
4.9/5
(30)

Examples of _____ processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.

(Multiple Choice)
4.9/5
(38)

A(n) _____ describes how things should be done.

(Short Answer)
4.8/5
(31)

The _____ process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end.

(Multiple Choice)
4.8/5
(42)

Which of the following activities is a part of the planning process of the Scrum?

(Multiple Choice)
4.8/5
(31)
Showing 21 - 40 of 76